2019 Street Rehab Project

Click here to view the complete project details including scope and locations.

View All Posts

Jul 29

Update for week of July 29

Posted on July 29, 2019 at 8:38 AM by John Guccione

Birchwood Ave:     ACTIVE
Placement of curb has been completed on the west side of Birchwood. The contractor will pour the sidewalk behind the new curb on Tuesday, weather permitting.   Impacted residents were notified last week.  Upon completion of sidewalk placement on the west side: the contractor will return late in the week to re-establish access on the west side. Removal of curb will begin on the east side of the street later in the week. Impacted residents will receive notice at their property previous to any impacts.

WarringtonACTIVE
Concrete placement continues this week on the east side of Warrington. The contractor is pouring the carriage sidewalk on the north end of Warrington and completing curb repairs on the south end.   Impacted residents were notified last week.  Upon completion of the east side:the contractor will return late in the week to re-establish access on the east side. Removal of curb will begin on the west side of the street later in the week. Impacted residents will receive notice at their property previous to any impacts.

Castlewood, Cranshire, Montgomery, Chatham, Peartree & Village Green: 90% complete
Paving has been completed. Restoration of parkway areas will be completed by the end of this week. Restoration is now 60% complete.

Meadow Lane: Awaiting Concrete Crew Availability
Repairs to concrete curbs and sidewalk will take place in 1-2 weeks. Pavement removal will follow.