Woodland WM Project Update - July 29

Posted on July 29, 2019 at 8:26 AM by Tyler Dickinson

July 29, 2019


Work Completed Last Week:
The contractor installed new water main via directional drilling on Woodland Dr from Crabtree Ln to Hawthorne Pl. Once completed the contractor then began drilling operations on Woodland Dr, east of Hawthorne Pl.  

Anticipated Schedule for This Week:
The contractor will continue to install new water main via direction drilling operations on Woodland Drive from Hawthorne Pl to Woodbine Ct. The underground contractor that is responsible for the associated water main item installations (fire hydrants, valve, services, etc.) is anticipated to begin work later this week by installing the new water main to the Wilmot Rd main. The contractor will then move to install valve vaults and fire hydrants on Woodland Dr. 

Percentage Complete: 19%

Neighborhood Impacts:
Construction operations will necessitate daily lane closures during working hours which may result in delays to local vehicular traffic. Caution shall be practiced through the construction work zone, and the Village asks that residents be alert for workers and construction equipment.

The Village appreciates your patience while we complete this improvement. If you have any questions or need additional information, please contact the Village of Deerfield Engineering Department at 847-317-2490.

Please be advised that the information communicated here is a forecast of proposed operations which may change due to contractor availability and/or weather conditions.