2019 Woodland Watermain Project

Click here to view the complete project details including scope and locations.

View All Posts

Jul 12

Woodland WM Project Update - July 12

Posted on July 12, 2019 at 3:29 PM by Tyler Dickinson

July 12, 2019

Work Completed This Week:

The contractor continued directionally drilling and pot-holing for existing utilities on Woodland Dr from Crabtree Ln to Stratford Rd.

Anticipated Schedule for Next Week:

The contractor will continue to install new water main via direction drilling operations on Woodland Drive from Crabtree Ln to Hawthorne Pl.
 

Percentage Complete: 15%

Neighborhood Impacts:

Construction operations will necessitate daily lane closures during working hours which may result in delays to
local vehicular traffic. Caution shall be practiced through the construction work zone, and the Village asks that residents be alert for workers and construction equipment.

The Village appreciates your patience while we complete this improvement. If you have any questions or need additional information, please contact the Village of Deerfield Engineering Department at 847-317-2490.

Please be advised that the information communicated here is a forecast of proposed operations which may change due to contractor availability and/or weather conditions.