Update for Week of 7/8/2019

Posted on July 8, 2019 at 8:52 AM by John Guccione

Birchwood Ave:
Storm Sewer repairs have been completed on Birchwood. Replacement of concrete curbs and sidewalks will take place in approximately 2 weeks.

Castlewood, Cranshire, Montgomery, Chatham, Peartree & Village Green:
This week, the contractor will work to restore parkway areas, prepare driveway approaches for paving and perform road patching on the subsurface of Cranshire Court and Pear Tree (where storm sewer replacements occurred). It is expected that the final surface course paving will take place on, or near Wednesday July 17th.

Warrington Road:
Work will begin this week to remove concrete curbs and sidewalk (on the east side of Warrington) in preparation for concrete placement (either late this week, or early next week). Once curbs and sidewalks have been removed, the contractor will restore access using aggregate (stone) ramps. Residents who will experience driveway impacts, will be notified 48-72 hours previous to impacts. 

Meadow Lane:
Underground work has been completed. Repairs to concrete curbs and sidewalk will take place in 3-4 weeks. Pavement removal will follow.