2019 Woodland Watermain Project

Click here to view the complete project details including scope and locations.

View All Posts

Jul 05

Woodland WM Project Update - July 5

Posted on July 5, 2019 at 4:25 PM by Tyler Dickinson

July 5, 2019

Work Completed This Week:
The contractor continued pot-holing for existing utilities from Crabtree Ln to Stratford Rd.

Anticipated Schedule for Next Week:
The contractor will continue to install new water main via direction drilling operations on Woodland Drive from Crabtree Ln to Hawthorne Pl.  

Percentage Complete: 15%

Neighborhood Impacts:
Construction operations will necessitate daily lane closures during working hours which may result in delays to local vehicular traffic. Caution shall be practiced through the construction work zone, and the Village asks that residents be alert for workers and construction equipment.

The Village appreciates your effort in helping to complete this improvement. If you have any questions or require special assistance during construction, please contact the Village of Deerfield Engineering Department at 847-317-2490 and request to speak with someone regarding the Woodland Subdivision Water Main Project.

Please be advised that the information communicated here is a forecast of proposed operations which may change due to contractor availability and/or weather conditions.