2019 Street Rehab Project

Click here to view the complete project details including scope and locations.

View All Posts

Jul 02

Underground Work Begins July 3rd on Birchwood Ave

Posted on July 2, 2019 at 9:47 AM by John Guccione

Birchwood Ave
Storm Sewer repairs will begin Wednesday July 3rd.  There will be no work on July 4th.  However, the contractor will return to complete the underground work on Friday, July 5th.  Once underground is completed the contractor will be able to schedule concrete curb and sidewalk replacement. 

Castlewood, Cranshire, Montgomery, Chatham, Peartree & Village Green:
This week and next, the contractor will work to restore parkway areas and prepare driveway approaches for paving. It is expected that the final surface course paving will take place in the next 2-3 weeks. 

Warrington Road:
Underground work has been completed. Repairs to concrete curbs and sidewalk will take place in 1-2 weeks. Pavement removal will follow.

Meadow Lane:
Underground work has been completed. Repairs to concrete curbs and sidewalk will take place in 3-4 weeks. Pavement removal will follow.