2019 Woodland Watermain Project

Click here to view the complete project details including scope and locations.

View All Posts

Jun 28

Woodland WM Project Update - June 28

Posted on June 28, 2019 at 6:41 PM by Tyler Dickinson

6/28/12019

Work Completed:

The contractor installed new water main via directional drilling operations on Woodland Dr from Oakwood Pl to Crabtree Ln.


Anticipated Schedule for Next Week:

The contractor will continue pot-holing existing utilities from Crabtree Ln to Stratford Rd. 
The contractor will not work on July 4 and does not anticipate working on July 5. 

Percentage Complete: 15%

Neighborhood Impacts:

Construction operations will necessitate daily lane closures during working hours which may result in delays to
local vehicular traffic. Caution shall be practiced through the construction work zone, and the Village asks that residents be alert for workers and construction equipment.

The Village appreciates your effort in helping to complete this improvement. If you have any questions or require special assistance during construction, please contact the Village of Deerfield Engineering Department at 847-317-2490 and request to speak with someone regarding the Woodland Subdivision Water Main Project.

Please be advised that the information communicated here is a forecast of proposed operations which may change due to contractor availability and/or weather conditions.