Greenwood Weekly Project Update - June 28

Posted on July 5, 2019 at 4:23 PM by Tyler Dickinson

June 28, 2019


Work Completed:

The required road closure of Greenwood Avenue from Waukegan Road to Chestnut Street and respective detour route via Hazel Avenue was implemented on June 17. Additional information regarding this closure can be found at
http://www.deerfield.il.us/CivicAlerts.aspx?AID=327.

This week, the contractor worked to install various underground utility improvements between Wilmot Rd and Chestnut St last week.


Anticipated Schedule for Next Week:

The contractor anticipates completing the various underground utility improvements west of Chestnut St on Monday. Then beginning on Tuesday, the contractor will commence water main installation via open-cut methods between Chestnut St and Waukegan Rd. The contractor will not be working on July 4 or July 5.

Percentage Complete: 10%

Neighborhood Impacts:

The various underground utility improvements west of Chestnut St
require daytime full closures of Greenwood Ave while the work is being completed. When a full closure is required, detours utilizing local roads will be implemented. The closure location and detour route, will vary as the contractor moves east and completes these repairs at various locations.

The Village appreciates your effort in helping to complete this improvement. If you have any questions or require special assistance during construction, please contact the Village of Deerfield Engineering Department at 847-317-2490 and request to speak with someone regarding the Greenwood Avenue Project.

Please be advised that the information communicated here is a forecast of proposed operations which may change due to contractor availability and/or weather conditions.