Construction Update for week of 3/27/2017

Posted on March 24, 2017 at 2:55 PM by John Guccione

Weather permitting, the contractor plans to complete storm sewer installation on Pine Street mid next week. Once this underground work is completed, the contractor will begin removing concrete sidewalks and curbs along the eastern portion of Pine Street.  Access to residential driveways will be maintained using temporary driveways made of aggregate stone material. Residents may experience minor access delays of 15 to 20 minutes while the concrete is removed and aggregate ramps are installed.

Once removal of sidewalk and curbs is completed, the contractor will prepare for the placement of new concrete curb.

Residents that will experience driveway access issues resulting from concrete pours will be notified using this system and by physical notification 48 to 72 hours prior to impacts.