Blog module icon

2019 Street Rehab Project

Click here to view the complete project details including scope and locations.

Dec 02

Final Street Rehab Update 12/2/2019

Posted on December 2, 2019 at 8:55 AM by John Guccione

 

All locations are now considered 100% complete with only punch list items remaining.  Punch list items include work such as: clean up, parkway restoration, brick replacement and a few remaining driveway approach repairs. In addition to the aforementioned items, the contractor will also be cleaning out drainage structures and other public utility structures, ensuring they are clear of debris.

Village wide pavement marking
is planned to take place tomorrow and through the end of the week, as weather permits.  Cross walks and stop bars will be placed with minimal impacts to the travelling public. Please exercise patience and drive carefully in the proximity of this operation.

This will be the final construction update for the 2019 Street Rehab Project.
The Village thanks all of our residents for their patience and understanding through this past construction season. Residents with any remaining questions or concerns relative to the 2019 Street Rehab Project may contact the Engineering Department at 847-317-2490.

Please note that the project has a warranty period of 1 year. Village staff will inspect all locations in the Spring of 2020 to address any items remaining from the 2019 season, and will also inspect again in August of 2020 to identify any warranty items.
_______________________

Berkeley Court:  100% complete
Birchwood Ave:  100% complete
Castlewood Ln., Cranshire, Chatham, Peartree & Village Green: 100% complete
Meadow Lane: 100% complete
Rosemary Terrace: 100% complete
Warrington Road 100% complete
Wilmot Road: 100% complete
Woodland Subdivision:100% complete

Nov 25

Update for week of November 25

Posted on November 25, 2019 at 7:21 AM by John Guccione

Status provided per location, sorted in alpha order.   In addition to the items provided below, the contractor will also be cleaning out drainage structures and other public utility structures, ensuring they are clear of debris.

_______________________
Berkeley Court:  
ACTIVE  99% complete 

Minor parkway restoration remains.

Birchwood Ave.:   100% complete

Castlewood Ln., Cranshire, Chatham, Peartree & Village Green: 100% complete


Meadow Lane: ACTIVE  99% complete 
Minor parkway restoration and some driveway restoration remains. 

Rosemary Terrace: 
ACTIVE 99% complete 
Minor parkway restoration remains. Placement of permanent pavement marking in planned for this week near Rosemary and Deerfield Road (to be completed as weather permits).

Warrington Road ACTIVE 99% complete 
Surface paving completed last week. Minor parkway restoration and some driveway restoration remains. 

Wilmot Road (Greenwood to North Ave): ACTIVE  99% complete 

Minor parkway restoration remains.

Woodland SubdivisionACTIVE 99% complete 
Surface paving completed last week. Minor parkway restoration and some driveway restoration remains. 
Nov 18

Update for week of November 18

Posted on November 18, 2019 at 7:14 AM by Tyler Dickinson

In addition to the items noted below, pavement markings and minor punch list items remain at all locations.
_______________________
Berkeley Court:  
ACTIVE  99% complete 

Paving completed on Friday 11/8. Minor parkway restoration remains.

Birchwood Ave.:   100% complete

Castlewood Ln., Cranshire, Chatham, Peartree & Village Green: 100% complete


Meadow Lane: ACTIVE  99% complete 
Driveway restoration remains. 

Rosemary Terrace: 
ACTIVE 99% complete 
Minor parkway restoration remains. Placement of permanent pavement marking near Rosemary and Deerfield Road to be completed as weather permits.

Warrington Road ACTIVE 95% complete 
Mainline paving completed on Saturday 11/9. The paving contractor anticipates completing the remaining final paving near intersections this week (possibly as early as Tuesday) as weather permits. 

Wilmot Road (Greenwood to North Ave): ACTIVE  99% complete 

Minor parkway restoration remains.

Woodland SubdivisionACTIVE 90% complete 
Final paving taking place today. Contractor will return for driveway restoration, minor parkway restoration, and pavement markings as weather permits.