May 22

Project Update

Posted on May 22, 2018 at 8:14 AM by John Guccione

SEE BELOW FOR CONSTRUCTION UPDATES FOR LOCATIONS CURRENTLY UNDER CONSTRUCTION.

*PLEASE NOTE THIS SCHEDULE IS WEATHER AND CONTRACTOR DEPENDENT *

Byron Court
Underground utility repairs began today on Byron Court and will take two days to complete. The contractor will begin removing concrete curbs and sidewalk as early as Wednesday afternoon, with a potential curb pour on Thursday or Friday of this week. Residents will receive a physical notification pending completion of underground repairs.

Central Ave and Kenmore Ave

The contractor will return to place the final lift of asphalt this Thursday.

As part of this work, fresh oil will be placed on the street previous to paving. This oil allows for a better bond of the new pavement to the existing roadway and lengthens the service life of the new pavement. Residents are advised to drive slowly during this time to prevent oil from splashing on their vehicles. The contractor will install FRESH OIL signs to notify motorists.

Paving operations often include heavy truck traffic and may present access delays to residential driveways and to through traffic. During this time and if possible, please avoid the construction operations and utilize alternate routes. All driveways and roadways will be accessible at the completion of the work day.

Bristol Estates & Bristol Drive

The contractor will return to place the final lift of asphalt beginning this Friday, May 25th. They will begin by paving intersections first, then return to pave the main line on Tuesday May 29.

As part of this work, fresh oil will be placed on the street previous to paving. This oil allows for a better bond of the new pavement to the existing roadway and lengthens the service life of the new pavement. Residents are advised to drive slowly during this time to prevent oil from splashing on their vehicles. The contractor will install FRESH OIL signs to notify motorists.

Paving operations often include heavy truck traffic and may present access delays to residential driveways and to through traffic. During this time and if possible, please avoid the construction operations and utilize alternate routes. All driveways and roadways will be accessible at the completion of the work day.

Oxford Road

The contractor is currently removing curbs in preparation to pour concrete curbs on Wednesday May 23rd. Approximately 1/3 of residents will experience driveway access impacts. Therefore, the Village is allowing the contractor to remove and replace curbs on both sides of the street at the same time. Residents at this location will receive a physical notification containing additional details today.  Pavement removal will begin next week.

Residents should also note that pavement removal operations will begin next week.

Osterman Ave & Somerset  Ave
Pavement removal on-hold, pending the completion of pavement removal operations at the Oxford location.

May 16

Road Closure Tomorrow on Central Ave (9 AM to 10:30 AM)

Posted on May 16, 2018 at 3:09 PM by John Guccione

This is a courtesy notice to inform you that on Thursday 5/17/2018 the contractor will place pavement sealant material along the curb-lines and down the center-line of Central Avenue.  Placement of this material will result in a complete closure of Central Avenue from 9 AM to 10:30 AM.  Once placed, this material requires 30 minutes to cure and then can be driven on with no issues.

Due to the complete closure of Central Avenue, we ask residents who require movement in or out Central Ave between 9 AM and 10:30 AM to relocate their vehicles outside Central Avenue between Castlewood Lane and Wilmot Road. Please note that the contractor will halt operations for any emergency vehicles.

The contractor will return next week to place the final surface course which will complete the project scope on Central Avenue.
jbandresultsimage2-1-small Jband-1_web-200-SMALL
The Village appreciates your effort in helping to complete this improvement. If you have any questions or need additional information, please contact the Deerfield Engineering Department at 847-317-2490 and request to speak with someone regarding the project. You can also reach Project Manager John Guccione on his mobile phone at 847-561-1851.


The Village of Deerfield website maintains weekly updates regarding construction progress. Additionally, residents may subscribe to Construction Notifications by visiting www.deerfield.il.us. 

Please drive carefully through construction zones.

May 11

Next Week's Schedule - Bristol, Osterman, Somerset, & Oxford

Posted on May 11, 2018 at 6:56 PM by Tyler Dickinson

SEE BELOW FOR CONSTRUCTION UPDATES FOR LOCATIONS CURRENTLY UNDER CONSTRUCTION.

*PLEASE NOTE THIS SCHEDULE IS WEATHER AND CONTRACTOR DEPENDENT *

Bristol Estates & Bristol Drive

On Monday, the contractor plans to begin paving Bristol Estates and Bristol Drive. This work may require the contractor to pave on Tuesday to finish this area. This work will be the first of two layers of asphalt to be installed with the second and final surface layer taking place at a later date. This first layer is intended to provide a smooth surface for the final surface layer.

As part of this work, fresh oil will be placed on the street early Monday morning. This oil allows for a better bond of the new pavement to the existing roadway and lengthens the service life of the new pavement. Residents are advised to drive slowly during this time to prevent oil from splashing on their vehicles. The contractor will install FRESH OIL signs to notify motorists.

Paving operations often include heavy truck traffic and may present access delays to residential driveways and to through traffic. During this time and if possible, please avoid the construction operations and utilize alternate routes. All driveways and roadways will be accessible at the completion of the work day.

Osterman Ave & Somerset  Ave

Access to driveways that were previously impacted were reinstated today, allowing those that were previously parked on the street back into their driveways. On Monday, the contractor will begin curb removals along the opposite side of these streets. For those whose driveways will be impacted, please remember to not park within the construction limits during this time. If curbs are poured Tuesday as planned, residents should expect to be able to return to their driveways by the end of the week.

By the end of the week, the contractor anticipates beginning the required underground work on Osterman.

Oxford Road

Next week, the contractor will continue to work on the upgrades to the underground infrastructure and anticipates completing this stage of the work by the end of the week.

Once the underground is completed, the contractor will then begin the removals of broken and deficient curbs and sidewalks throughout the roadway limits. This work is anticipated to begin the in next week or two. Further communication will follow prior to any impacts to driveways.