Blog module icon

All Blog


Find out what's happening in the blog. Below is a list of blog items.

Aug 18

Brierhill Construction Update - 8/18/2017

Posted to 2017 Brierhill Rd Project by Tyler Dickinson

Deerfield Logo small

Village of Deerfield

Brierhill Road Project Construction Update – 8/18/2017

LAST WEEK

This week, the contractor began parkway restoration, concrete driveway installation, and continued brick driveway installation.

SCHEDULE

Next week, the contractor will complete all driveways with the asphalt driveways planned to take place mid to late week next week. The reinstallation of asphalt driveway will impact driveway access only during the actual installation which is generally under a couple hours. Residents will be notified prior to the work taking place. The contractor will also be working to install new topsoil within the parkways.


Once the parkways are filled with topsoil, the contractor will reinstall the mailboxes and install the new trees. For the trees, the Village Arborist performed a walk through of the site and recommended the proposed locations. However, due to existing shade from nearby trees, these locations are limited.

THANK YOU FOR YOUR CONTINUED PATIENCE.

  Please be advised that the information communicated here is a forecast of proposed operations, which may change due to contractor availability and/or weather conditions.

Jun 23

Construction Forecast for the week of 6/26/2017

Posted to 2017 Street Rehab Project by John Guccione

This construction forecast is for the week of June 26, 2017.

Garand Drive 
Underground sewer repairs and concrete curb and sidewalk installation has been completed on Garand Drive. Pavement removal could begin towards the middle of next week (weather permitting). Additional notice will follow prior to pavement removal. As pavement removal operations could present delayed access to residential driveways.

Wincanton Drive
Construction layout and utility locates have been completed in preparation for the upcoming construction project. Underground sewer work could begin as early as July 5th.

Pine Street
Sod placement is complete. The only remaining work at this location is the placement of asphalt surface pavement, which will take place in the next two months. 

Fair Oaks Avenue
Sod placement is complete. The only remaining work at this location is the placement of asphalt surface pavement, which will take place in the next two months. 

Continue Reading...