Blog module icon

All Blog


Find out what's happening in the blog. Below is a list of blog items.

May 30

Brierhill Rd Restoration - 5/30/18

Posted to 2017 Brierhill Rd Project by Tyler Dickinson

Deerfield Logo small

Village of Deerfield

Brierhill Road Project Restoration

Brierhill Rd Residents,


The contractor will be returning this spring to replace sod or reseed any parkway areas that did not take or survive the winter. Once these locations have been replaced/reseeded, we ask that residents help out by watering any new sod/seed daily for the first two weeks. While onsite, the contractor will also be performing other miscellaneous tasks to correct any deficient works items related to last year’s construction project. Timing of this work has not been established but this work should take place before July.


Oct 12

Paving on Wincanton, East Canton & West Canton Court Tomorrow.

Posted to 2017 Street Rehab Project by John Guccione

This is a courtesy notice to inform you that surface paving will take place tomorrow, October 13, 2017 on Wincanton, East Canton & West Canton Court.  Paving operations will begin at 7 am and should be completed by 4 pm.

In efforts to achieve optimal smoothness, we ask that you refrain from traveling over the fresh pavement. Therefore, we ask that vehicles be relocated prior to paving operations.

Once paving and compaction is completed, residents will have full access to their driveways 30-40 minutes after compaction (rolling) of asphalt mix.

During paving operations, please note that homeowners will have access to their property at all times via the new sidewalk. However, due to limited space during daytime operations, access to driveways may be delayed or denied at times. Please allow ample time for relocation of vehicles and temporary delays that may occur. Though driveway access may be denied during paving operations, access will be re-established at the end of daytime operations.

The Village appreciates your effort in helping to complete this improvement. If you have any questions or need additional information, please contact the Village of Deerfield Engineering Department at 847-317-2490 and request to speak with someone regarding the Project.

Overnight parking on adjacent streets will be permitted during this phase of construction. The Village of Deerfield Police Department has been notified that residents within this area will be parking overnight on Village streets. During the day, between 7:00 AM and 7:00 PM, please park your vehicle(s) away from the construction area to allow the contractor complete access to the job site. 

Sep 04

Crabtree & Elmwood - Curb Removal/Replacement

Posted to 2018 Street Rehab Project by Tyler Dickinson

Tomorrow, the contractor will begin removing concrete curbs on Crabtree Lane and the south side of Elmwood Ave in preparation for the placement of new concrete curbs on Friday 9/7/2018, weather permitting.

Upon completing removal on Wednesday, the contractor will restore driveway access using aggregate material (stone). The temporary stone driveway will be removed on Friday morning at 7:30 AM when the new curb is scheduled to be poured. After the curb has been poured, residents whose driveways are impacted will not be able to access their driveways until the concrete cures (3-5 Days) and passes strength tests.

If you are concerned with parking on the street overnight, the Village recommends taking a neighborly approach to this inconvenience. If possible, please coordinate with your neighbors to allow for overnight parking on their driveway while access to your driveway is impacted. Residents that require daily access to their driveways are encouraged to contact the engineering department.

The Village appreciates your effort in helping to complete this improvement. If you have any questions or need additional information, please contact the Deerfield Engineering Department at 847-317-2490 and request to speak with someone regarding the project, (or reach John Guccione on his mobile phone at 847-561-1851 (jguccione@deerfield.il.us)).

Please drive carefully through construction zones.