Blog module icon

All Blog


Find out what's happening in the blog. Below is a list of blog items.

Jul 27

Construction Update: Week of July 26

Posted to 2021 Street Rehabilitation Project by John Guccione

Ambleside, Dimmeydale, and Windcrest
Directional boring for street light conduit is planned to begin in the next couple weeks, pending contractor availability. The final roadway surface placement will be coordinated with other locations and the completion of the street light work in around 2-3 weeks.   
 
Greenwood Avenue
Detector loops for Waukegan Road traffic signal is planned for the end of this week, pending contractor availability. Once completed, the contractor will complete the remaining sidewalk work along Waukegan Rd. The final roadway surface placement will be coordinated with other locations in around 2-3 weeks.
 
Elder Lane
Next week (the week of August 2nd) the contractor’s underground team will return to perform some additional storm sewer and water service improvements. The storm sewer improvements will work in conjunction with the new curb which is planned to be installed in the next 2-3 weeks.
 

Reminder that trash collection at all locations has been rescheduled for early pickup, starting at 6:30am. This is in an effort to avoid any conflicts with the construction crews.

Jun 25

Stormwater Management Plan REPORT

Posted to Deerfield Village Wide Drainage Study by John Guccione

In early 2020, the Village initiated a contract with an area consultant to developed a Village wide Stormwater Master Plan. This plan is designed to analyze and model the Village’s storm sewer system to determine deficient areas and provide improvement recommendations to those areas.  In all, there were 42 flood study areas that were identified where detailed drainage analyses was performed.


This plan has been submitted and reviewed by Village staff and is in its final draft form. As public input and resident interaction was a large part of the historical data collection, the Village is making the final draft available to residents for a 30 day public commenting period. During this time, residents are encouraged to review this report and provide any comments or questions to Village staff. The Village understands that this study and its associated computer model may not fit every situation perfectly, but the Village hopes that the information contained within the report is informative and helpful.


Public comments and questions can be emailed to the Engineering Department at engineering@deerfield.il.us. Please include "STORMWATER MASTER PLAN" in the subject line when sending in comments. Comments will be accepted until July 26th.

DOWNLOAD-REPORT